The Hub
Our housing guidance site
Essential guide to dealing with voids.
Responsible people: Dermott Mulan, Harjinder Birdi, Sukhi Nijjar
Procedure will be reviewed in January 2025
This procedure is part of the Council’s Voids Policy. It sets out what needs to be done to get a void property ready for a new tenancy. The Voids Policy explains our approach to repairing and letting void properties to our residents, most importantly housing applicants, in a way that clearly sets out the standard of service that can be expected. This procedure on the other hand focuses directly on what needs to be done by Council officers and contractors, when and by whom.
Click here for the full guidance.
The housing management manual on updating Northgate.
The Voids repairs team collect property elements after the initial inspection. These need adding to NEC to allow a property to be let. It is a good idea to get these added as soon as they are collected so time isn't wasted after a property has been handed back.
The essential elements are:
GARDEN What type of garden there is (front, back, communal)
OWNENTRANCE Does it have it's own entrance
SINGLEBEDS Number of single beds
DOUBLEBEDS Number of double beds
FLOORLEVEL Property Floor Level
LIFT Accessible lift
ADAPTATION Property Adaptation (eg. Disabled use)
STEPSIN Number of internal steps
STEPSOUT Number of external steps
HEATTYPE Heating Type
Here is the guide to "Elements - find, create or amend property elements" to add these to NEC.
If any aids or hospital beds have been left, more details are here.
Amended 7/9/20